Construction Updates

New High School Renderings

Exterior

Exterior view of the new high school

Exterior

Exterior view of the new high school

Exterior

Exterior view of the new high school

Exterior

Exterior view of the new high school

Interior

Interior view of the new gym

Interior

Interior view of the new gym

Interior

Interior view of the new gym

Interior

Interior view of the new library/media center

Interior

Interior view of the new library/media center

New High School Progress

Crew

February 20, 2024 – Site work begins as crews tear up the concrete sidewalk and fence off the construction area as they begin building Fatima's new high school.

Crew

February 20, 2024 – Site work begins as crews tear up the concrete sidewalk and fence off the construction area as they begin building Fatima's new high school.

Crew

February 20, 2024 – Site work begins as crews tear up the concrete sidewalk and fence off the construction area as they begin building Fatima's new high school.

Crew

February 20, 2024 – Site work begins as crews tear up the concrete sidewalk and fence off the construction area as they begin building Fatima's new high school.

Crew

February 26, 2024 -- Crews are working to dismantle the old superintendent's office, making way for Fatima's new high school.

Picture

February 26, 2024 -- Crews are working to dismantle the old superintendent's office, making way for Fatima's new high school.

Picture

March 6, 2024 -- Crews continue working to dismantle the old superintendent's office, making way for Fatima's new high school and gym.

Picture

March 6, 2024 -- Crews continue working to dismantle the old superintendent's office, making way for Fatima's new high school and gym.

Picture

March 19, 2024 -- The crew continues site work on the new high school as they finish the demolition of the old admin. building.

Picture

March 19, 2024 -- The crew continues site work on the new high school as they finish the demolition of the old admin. building.

Picture

March 19, 2024 -- The crew continues site work on the new high school as they finish the demolition of the old admin. building.

Picture

March 19, 2024 -- The crew continues site work on the new high school as they finish the demolition of the old admin. building.

Picture

March 27, 2024 -- Crews continue site preparation work ahead of base material, footings and pier installation.

Picture

March 27, 2024 -- Crews continue site preparation work ahead of base material, footings and pier installation.

Overhead

March 27, 2024 -- Crews continue site preparation work ahead of base material, footings and pier installation.

Footings

April 10, 2024 -- Footings are prepared for the new building.

Footings

April 10, 2024 -- Footings are prepared for the new building.

Footings

April 10, 2024 -- Footings are prepared for the new building.

Pier

April 22, 2024 -- The building begins to take shape as pier work is completed.

Pier

April 22, 2024 -- The building begins to take shape as pier work is completed.

Pier

April 22, 2024 -- The building begins to take shape as pier work is completed.

Concrete

May 17, 2024 -- Concrete is poured into the forms, as the building continues to take shape.

Concrete

May 17, 2024 -- Concrete is poured into the forms, as the building continues to take shape.

Construction

July 18, 2024 -- The new entrance to the gym lobby begins to take shape.

Concrete

July 18, 2024 -- Concrete work continues on the new high school and gym.

Walls

July 18, 2024 -- Walls begin to take shape for the new gym.

Walls

July 18, 2024 -- Concrete work continues on the new high school and gym.

Utility

August 1, 2024 -- Utilities begin to take shape.

Workers

August 1, 2024 -- Concrete is smoothed as the new high school continues to take shape.

Steel

August 1, 2024 -- Steel structure is brought in for the framing of the new gym.

Walls

August 1, 2024 -- Block work continues as the new building continues to take its shape.

Block

August 1, 2024 -- Block work continues as the new building continues to take its shape.

Steel

August 1, 2024 -- The steel structure for the new gym continues to take shape.

Walls

August 29, 2024 -- The steel structure for the new gym continues to take shape.

Walls

August 29, 2024 -- The block walls for the new gym and lockerroom continue to take shape.

Walls

August 29, 2024 -- The block walls for the new gym and lockerroom continue to take shape.

Walls

August 29, 2024 -- The block walls for the new gym and lockerroom continue to take shape.

Walls

September 1, 2024 -- The block walls for the new gym and locker room continue to take shape.

Walls

September 1, 2024 -- The block walls for the new gym and locker room continue to take shape.

Roof

September 1, 2024 -- The roofing for the new gym and locker room continue to take shape.

Steel

September 10, 2024 -- Steel structure is assembled for the new high school.

Steel

September 10, 2024 -- Steel structure is assembled for the new high school.

Steel

September 10, 2024 -- Steel structure is assembled for the new high school.

Steel

September 10, 2024 -- Steel structure is assembled for the new high school.

Steel

September 10, 2024 -- Steel structure is assembled for the new high school.

construction

September 11, 2024 -- The wrestling room takes shape.

overhead

September 11, 2024 -- Overhead shots of current progress.

overhead

September 11, 2024 -- Overhead shots of current progress.

overhead

September 11, 2024 -- Overhead shots of current progress.

overhead

September 11, 2024 -- Overhead shots of current progress.

overhead

September 11, 2024 -- Overhead shots of current progress.

View

October 23, 2024 – First look at the new hallway that separates the gym and new addition from the rest of the high school.

Picture

October 23, 2024 – Locker rooms begin to take shape in the new gym.

View

October 23, 2024 – First look from what will eventually be the second floor of the new high school.

View

October 23, 2024 – First look from what will eventually be the second floor of the new high school.

First

December 12, 2024 – Construction continues on the first level of the new high school.

Second

December 12, 2024 – Construction continues with the finishing of concrete for the second level of the new high school.

Framing

December 12, 2024 – Construction continues as framing is built for the new high school.

Brick

December 12, 2024 – Construction continues as brickwork begins on the exterior of the new high school.

Brick

December 12, 2024 – Construction continues as brickwork begins on the exterior of the new high school.

Superintendent's Office

House

October 12, 2023 – Preparation is complete for demolition of the house on 147 E. Main St., making way for the new Superintendent’s office. Anticipated completion of the new office building is March, 2024.

Side

October 12, 2023 – Preparation is complete for demolition of the house on 147 E. Main St., making way for the new Superintendent’s office. Anticipated completion of the new office building is March, 2024.

Construction

October 12, 2023 – Preparation is complete for demolition of the house on 147 E. Main St., making way for the new Superintendent’s office. Anticipated completion of the new office building is March, 2024.

House

October 13, 2023 – Demolition of the house on 147 E. Main St. has begun, making way for the new Superintendent’s office. Anticipated completion of the new office building is March, 2024.

House

October 13, 2023 – Demolition of the house on 147 E. Main St. has begun, making way for the new Superintendent’s office. Anticipated completion of the new office building is March, 2024.

House

October 13, 2023 – Demolition of the house on 147 E. Main St. has begun, making way for the new Superintendent’s office. Anticipated completion of the new office building is March, 2024.

Picture

October 13, 2023 – Demolition of the house on 147 E. Main St. has begun, making way for the new Superintendent’s office. Anticipated completion of the new office building is March, 2024.

Picture

October 13, 2023 – Demolition of the house on 147 E. Main St. has begun, making way for the new Superintendent’s office. Anticipated completion of the new office building is March, 2024.

Picture

October 24, 2023 – Construction continues on the new superintendent’s office building. The crew has begun working to install footings for the new building.

Construction

October 24, 2023 – Construction continues on the new superintendent’s office building. The crew has begun working to install footings for the new building.

Truck

October 24, 2023 – Construction continues on the new superintendent’s office building. The crew has begun working to install footings for the new building.

Truck

October 24, 2023 – Construction continues on the new superintendent’s office building. The crew has begun working to install footings for the new building.

Picture

November 8, 2023 – Construction continues on the new superintendent’s office building. The crew has finished the foundation for the new building.

Picture

November 8, 2023 – Construction continues on the new superintendent’s office building. The crew has finished the foundation for the new building.

Picture

November 8, 2023 – Construction continues on the new superintendent’s office building. The crew has finished the foundation for the new building.

Picture

November 8, 2023 – Construction continues on the new superintendent’s office building. The crew has finished the foundation for the new building.

Concrete

December 5, 2023 -- The crew works to lay concrete for the flooring of the new superintendent's office.

Concrete

December 5, 2023 -- The crew works to lay concrete for the flooring of the new superintendent's office.

Concrete

December 5, 2023 -- The crew works to lay concrete for the flooring of the new superintendent's office.

Freshly

December 5, 2023 -- The crew works to lay concrete for the flooring of the new superintendent's office.

Freshly

December 5, 2023 -- The crew works to lay concrete for the flooring of the new superintendent's office.

Picture

December 7, 2023 -- Concrete work continues as the driveway for the new superintendent's office takes shape.

Picture

December 7, 2023 -- Concrete work continues as the driveway for the new superintendent's office takes shape.

Picture

January 29, 2024 -- Construction continues as the steel skeleton is assembled for the new superintendent's office.

Picture

January 29, 2024 -- Construction continues as the steel skeleton is assembled for the new superintendent's office.

Concrete

February 6, 2024 -- Construction continues as concrete flooring is poured for the storage mezzanine.

Aerial

February 6, 2024 -- Construction continues as concrete flooring is poured for the storage mezzanine.

Aerial

February 6, 2024 -- Construction continues as concrete flooring is poured for the storage mezzanine.

Aerial

February 6, 2024 -- Construction continues as concrete flooring is poured for the storage mezzanine.

Metal

February 13, 2024 -- Construction continues as metal sheeting is going up, around the building.

Metal

February 13, 2024 -- Construction continues as metal sheeting is going up, around the building.

Metal

February 13, 2024 -- Construction continues as metal sheeting is going up, around the building.

Crews

March 6, 2024 -- Crews continue exterior work on the new superintendent's office.

Interior

March 6, 2024 -- Crews continue interior work on the new superintendent's office. First level, seen here.

Interior

March 6, 2024 -- Crews continue interior work on the new superintendent's office. Second level, seen here.

Interview

March 6, 2024 -- Crews continue interior work on the new superintendent's office. Second level, shop view, seen here.

Exterior

March 6, 2024 -- Crews continue exterior work on the new superintendent's office.

View

March 19, 2024 -- The crew continues work as the new lettering is added an additional exterior work is completed.

View

March 20, 2024 -- Drywall is in the process of being hung. All exterior doors and windows are now installed.

Interior

March 20, 2024 -- Drywall is in the process of being hung. All exterior doors and windows are now installed.

Interior

March 20, 2024 -- Drywall is in the process of being hung. All exterior doors and windows are now installed.

Picture

March 20, 2024 -- Drywall is in the process of being hung. All exterior doors and windows are now installed.

completed

May 29, 2024 -- Construction is complete and employees have moved into their new home.