For Mac OS users, there is a system setting that may not allow you to tab onto several types of elements in a web page. To change this setting:
Exterior view of the new high school
Exterior view of the new high school
Exterior view of the new high school
Exterior view of the new high school
Interior view of the new gym
Interior view of the new gym
Interior view of the new gym
Interior view of the new library/media center
Interior view of the new library/media center
Exterior view of the new high school
Exterior view of the new high school
Exterior view of the new high school
Exterior view of the new high school
Interior view of the new gym
Interior view of the new gym
Interior view of the new gym
Interior view of the new library/media center
Interior view of the new library/media center
February 20, 2024 – Site work begins as crews tear up the concrete sidewalk and fence off the construction area as they begin building Fatima's new high school.
February 20, 2024 – Site work begins as crews tear up the concrete sidewalk and fence off the construction area as they begin building Fatima's new high school.
February 20, 2024 – Site work begins as crews tear up the concrete sidewalk and fence off the construction area as they begin building Fatima's new high school.
February 20, 2024 – Site work begins as crews tear up the concrete sidewalk and fence off the construction area as they begin building Fatima's new high school.
February 26, 2024 -- Crews are working to dismantle the old superintendent's office, making way for Fatima's new high school.
February 26, 2024 -- Crews are working to dismantle the old superintendent's office, making way for Fatima's new high school.
March 6, 2024 -- Crews continue working to dismantle the old superintendent's office, making way for Fatima's new high school and gym.
March 6, 2024 -- Crews continue working to dismantle the old superintendent's office, making way for Fatima's new high school and gym.
March 19, 2024 -- The crew continues site work on the new high school as they finish the demolition of the old admin. building.
March 19, 2024 -- The crew continues site work on the new high school as they finish the demolition of the old admin. building.
March 19, 2024 -- The crew continues site work on the new high school as they finish the demolition of the old admin. building.
March 19, 2024 -- The crew continues site work on the new high school as they finish the demolition of the old admin. building.
March 27, 2024 -- Crews continue site preparation work ahead of base material, footings and pier installation.
March 27, 2024 -- Crews continue site preparation work ahead of base material, footings and pier installation.
March 27, 2024 -- Crews continue site preparation work ahead of base material, footings and pier installation.
April 10, 2024 -- Footings are prepared for the new building.
April 10, 2024 -- Footings are prepared for the new building.
April 10, 2024 -- Footings are prepared for the new building.
April 22, 2024 -- The building begins to take shape as pier work is completed.
April 22, 2024 -- The building begins to take shape as pier work is completed.
April 22, 2024 -- The building begins to take shape as pier work is completed.
May 17, 2024 -- Concrete is poured into the forms, as the building continues to take shape.
May 17, 2024 -- Concrete is poured into the forms, as the building continues to take shape.
July 18, 2024 -- The new entrance to the gym lobby begins to take shape.
July 18, 2024 -- Concrete work continues on the new high school and gym.
July 18, 2024 -- Walls begin to take shape for the new gym.
July 18, 2024 -- Concrete work continues on the new high school and gym.
August 1, 2024 -- Utilities begin to take shape.
August 1, 2024 -- Concrete is smoothed as the new high school continues to take shape.
August 1, 2024 -- Steel structure is brought in for the framing of the new gym.
August 1, 2024 -- Block work continues as the new building continues to take its shape.
August 1, 2024 -- Block work continues as the new building continues to take its shape.
August 1, 2024 -- The steel structure for the new gym continues to take shape.
August 29, 2024 -- The steel structure for the new gym continues to take shape.
August 29, 2024 -- The block walls for the new gym and lockerroom continue to take shape.
August 29, 2024 -- The block walls for the new gym and lockerroom continue to take shape.
August 29, 2024 -- The block walls for the new gym and lockerroom continue to take shape.
September 1, 2024 -- The block walls for the new gym and locker room continue to take shape.
September 1, 2024 -- The block walls for the new gym and locker room continue to take shape.
September 1, 2024 -- The roofing for the new gym and locker room continue to take shape.
September 10, 2024 -- Steel structure is assembled for the new high school.
September 10, 2024 -- Steel structure is assembled for the new high school.
September 10, 2024 -- Steel structure is assembled for the new high school.
September 10, 2024 -- Steel structure is assembled for the new high school.
September 10, 2024 -- Steel structure is assembled for the new high school.
September 11, 2024 -- The wrestling room takes shape.
September 11, 2024 -- Overhead shots of current progress.
September 11, 2024 -- Overhead shots of current progress.
September 11, 2024 -- Overhead shots of current progress.
September 11, 2024 -- Overhead shots of current progress.
September 11, 2024 -- Overhead shots of current progress.
October 23, 2024 – First look at the new hallway that separates the gym and new addition from the rest of the high school.
October 23, 2024 – Locker rooms begin to take shape in the new gym.
October 23, 2024 – First look from what will eventually be the second floor of the new high school.
October 23, 2024 – First look from what will eventually be the second floor of the new high school.
December 12, 2024 – Construction continues on the first level of the new high school.
December 12, 2024 – Construction continues with the finishing of concrete for the second level of the new high school.
December 12, 2024 – Construction continues as framing is built for the new high school.
December 12, 2024 – Construction continues as brickwork begins on the exterior of the new high school.
December 12, 2024 – Construction continues as brickwork begins on the exterior of the new high school.
February 20, 2024 – Site work begins as crews tear up the concrete sidewalk and fence off the construction area as they begin building Fatima's new high school.
February 20, 2024 – Site work begins as crews tear up the concrete sidewalk and fence off the construction area as they begin building Fatima's new high school.
February 20, 2024 – Site work begins as crews tear up the concrete sidewalk and fence off the construction area as they begin building Fatima's new high school.
February 20, 2024 – Site work begins as crews tear up the concrete sidewalk and fence off the construction area as they begin building Fatima's new high school.
February 26, 2024 -- Crews are working to dismantle the old superintendent's office, making way for Fatima's new high school.
February 26, 2024 -- Crews are working to dismantle the old superintendent's office, making way for Fatima's new high school.
March 6, 2024 -- Crews continue working to dismantle the old superintendent's office, making way for Fatima's new high school and gym.
March 6, 2024 -- Crews continue working to dismantle the old superintendent's office, making way for Fatima's new high school and gym.
March 19, 2024 -- The crew continues site work on the new high school as they finish the demolition of the old admin. building.
March 19, 2024 -- The crew continues site work on the new high school as they finish the demolition of the old admin. building.
March 19, 2024 -- The crew continues site work on the new high school as they finish the demolition of the old admin. building.
March 19, 2024 -- The crew continues site work on the new high school as they finish the demolition of the old admin. building.
March 27, 2024 -- Crews continue site preparation work ahead of base material, footings and pier installation.
March 27, 2024 -- Crews continue site preparation work ahead of base material, footings and pier installation.
March 27, 2024 -- Crews continue site preparation work ahead of base material, footings and pier installation.
April 10, 2024 -- Footings are prepared for the new building.
April 10, 2024 -- Footings are prepared for the new building.
April 10, 2024 -- Footings are prepared for the new building.
April 22, 2024 -- The building begins to take shape as pier work is completed.
April 22, 2024 -- The building begins to take shape as pier work is completed.
April 22, 2024 -- The building begins to take shape as pier work is completed.
May 17, 2024 -- Concrete is poured into the forms, as the building continues to take shape.
May 17, 2024 -- Concrete is poured into the forms, as the building continues to take shape.
July 18, 2024 -- The new entrance to the gym lobby begins to take shape.
July 18, 2024 -- Concrete work continues on the new high school and gym.
July 18, 2024 -- Walls begin to take shape for the new gym.
July 18, 2024 -- Concrete work continues on the new high school and gym.
August 1, 2024 -- Utilities begin to take shape.
August 1, 2024 -- Concrete is smoothed as the new high school continues to take shape.
August 1, 2024 -- Steel structure is brought in for the framing of the new gym.
August 1, 2024 -- Block work continues as the new building continues to take its shape.
August 1, 2024 -- Block work continues as the new building continues to take its shape.
August 1, 2024 -- The steel structure for the new gym continues to take shape.
August 29, 2024 -- The steel structure for the new gym continues to take shape.
August 29, 2024 -- The block walls for the new gym and lockerroom continue to take shape.
August 29, 2024 -- The block walls for the new gym and lockerroom continue to take shape.
August 29, 2024 -- The block walls for the new gym and lockerroom continue to take shape.
September 1, 2024 -- The block walls for the new gym and locker room continue to take shape.
September 1, 2024 -- The block walls for the new gym and locker room continue to take shape.
September 1, 2024 -- The roofing for the new gym and locker room continue to take shape.
September 10, 2024 -- Steel structure is assembled for the new high school.
September 10, 2024 -- Steel structure is assembled for the new high school.
September 10, 2024 -- Steel structure is assembled for the new high school.
September 10, 2024 -- Steel structure is assembled for the new high school.
September 10, 2024 -- Steel structure is assembled for the new high school.
September 11, 2024 -- The wrestling room takes shape.
September 11, 2024 -- Overhead shots of current progress.
September 11, 2024 -- Overhead shots of current progress.
September 11, 2024 -- Overhead shots of current progress.
September 11, 2024 -- Overhead shots of current progress.
September 11, 2024 -- Overhead shots of current progress.
October 23, 2024 – First look at the new hallway that separates the gym and new addition from the rest of the high school.
October 23, 2024 – Locker rooms begin to take shape in the new gym.
October 23, 2024 – First look from what will eventually be the second floor of the new high school.
October 23, 2024 – First look from what will eventually be the second floor of the new high school.
December 12, 2024 – Construction continues on the first level of the new high school.
December 12, 2024 – Construction continues with the finishing of concrete for the second level of the new high school.
December 12, 2024 – Construction continues as framing is built for the new high school.
December 12, 2024 – Construction continues as brickwork begins on the exterior of the new high school.
December 12, 2024 – Construction continues as brickwork begins on the exterior of the new high school.
October 12, 2023 – Preparation is complete for demolition of the house on 147 E. Main St., making way for the new Superintendent’s office. Anticipated completion of the new office building is March, 2024.
October 12, 2023 – Preparation is complete for demolition of the house on 147 E. Main St., making way for the new Superintendent’s office. Anticipated completion of the new office building is March, 2024.
October 12, 2023 – Preparation is complete for demolition of the house on 147 E. Main St., making way for the new Superintendent’s office. Anticipated completion of the new office building is March, 2024.
October 13, 2023 – Demolition of the house on 147 E. Main St. has begun, making way for the new Superintendent’s office. Anticipated completion of the new office building is March, 2024.
October 13, 2023 – Demolition of the house on 147 E. Main St. has begun, making way for the new Superintendent’s office. Anticipated completion of the new office building is March, 2024.
October 13, 2023 – Demolition of the house on 147 E. Main St. has begun, making way for the new Superintendent’s office. Anticipated completion of the new office building is March, 2024.
October 13, 2023 – Demolition of the house on 147 E. Main St. has begun, making way for the new Superintendent’s office. Anticipated completion of the new office building is March, 2024.
October 13, 2023 – Demolition of the house on 147 E. Main St. has begun, making way for the new Superintendent’s office. Anticipated completion of the new office building is March, 2024.
October 24, 2023 – Construction continues on the new superintendent’s office building. The crew has begun working to install footings for the new building.
October 24, 2023 – Construction continues on the new superintendent’s office building. The crew has begun working to install footings for the new building.
October 24, 2023 – Construction continues on the new superintendent’s office building. The crew has begun working to install footings for the new building.
October 24, 2023 – Construction continues on the new superintendent’s office building. The crew has begun working to install footings for the new building.
November 8, 2023 – Construction continues on the new superintendent’s office building. The crew has finished the foundation for the new building.
November 8, 2023 – Construction continues on the new superintendent’s office building. The crew has finished the foundation for the new building.
November 8, 2023 – Construction continues on the new superintendent’s office building. The crew has finished the foundation for the new building.
November 8, 2023 – Construction continues on the new superintendent’s office building. The crew has finished the foundation for the new building.
December 5, 2023 -- The crew works to lay concrete for the flooring of the new superintendent's office.
December 5, 2023 -- The crew works to lay concrete for the flooring of the new superintendent's office.
December 5, 2023 -- The crew works to lay concrete for the flooring of the new superintendent's office.
December 5, 2023 -- The crew works to lay concrete for the flooring of the new superintendent's office.
December 5, 2023 -- The crew works to lay concrete for the flooring of the new superintendent's office.
December 7, 2023 -- Concrete work continues as the driveway for the new superintendent's office takes shape.
December 7, 2023 -- Concrete work continues as the driveway for the new superintendent's office takes shape.
January 29, 2024 -- Construction continues as the steel skeleton is assembled for the new superintendent's office.
January 29, 2024 -- Construction continues as the steel skeleton is assembled for the new superintendent's office.
February 6, 2024 -- Construction continues as concrete flooring is poured for the storage mezzanine.
February 6, 2024 -- Construction continues as concrete flooring is poured for the storage mezzanine.
February 6, 2024 -- Construction continues as concrete flooring is poured for the storage mezzanine.
February 6, 2024 -- Construction continues as concrete flooring is poured for the storage mezzanine.
February 13, 2024 -- Construction continues as metal sheeting is going up, around the building.
February 13, 2024 -- Construction continues as metal sheeting is going up, around the building.
February 13, 2024 -- Construction continues as metal sheeting is going up, around the building.
March 6, 2024 -- Crews continue exterior work on the new superintendent's office.
March 6, 2024 -- Crews continue interior work on the new superintendent's office. First level, seen here.
March 6, 2024 -- Crews continue interior work on the new superintendent's office. Second level, seen here.
March 6, 2024 -- Crews continue interior work on the new superintendent's office. Second level, shop view, seen here.
March 6, 2024 -- Crews continue exterior work on the new superintendent's office.
March 19, 2024 -- The crew continues work as the new lettering is added an additional exterior work is completed.
March 20, 2024 -- Drywall is in the process of being hung. All exterior doors and windows are now installed.
March 20, 2024 -- Drywall is in the process of being hung. All exterior doors and windows are now installed.
March 20, 2024 -- Drywall is in the process of being hung. All exterior doors and windows are now installed.
March 20, 2024 -- Drywall is in the process of being hung. All exterior doors and windows are now installed.
May 29, 2024 -- Construction is complete and employees have moved into their new home.
October 12, 2023 – Preparation is complete for demolition of the house on 147 E. Main St., making way for the new Superintendent’s office. Anticipated completion of the new office building is March, 2024.
October 12, 2023 – Preparation is complete for demolition of the house on 147 E. Main St., making way for the new Superintendent’s office. Anticipated completion of the new office building is March, 2024.
October 12, 2023 – Preparation is complete for demolition of the house on 147 E. Main St., making way for the new Superintendent’s office. Anticipated completion of the new office building is March, 2024.
October 13, 2023 – Demolition of the house on 147 E. Main St. has begun, making way for the new Superintendent’s office. Anticipated completion of the new office building is March, 2024.
October 13, 2023 – Demolition of the house on 147 E. Main St. has begun, making way for the new Superintendent’s office. Anticipated completion of the new office building is March, 2024.
October 13, 2023 – Demolition of the house on 147 E. Main St. has begun, making way for the new Superintendent’s office. Anticipated completion of the new office building is March, 2024.
October 13, 2023 – Demolition of the house on 147 E. Main St. has begun, making way for the new Superintendent’s office. Anticipated completion of the new office building is March, 2024.
October 13, 2023 – Demolition of the house on 147 E. Main St. has begun, making way for the new Superintendent’s office. Anticipated completion of the new office building is March, 2024.
October 24, 2023 – Construction continues on the new superintendent’s office building. The crew has begun working to install footings for the new building.
October 24, 2023 – Construction continues on the new superintendent’s office building. The crew has begun working to install footings for the new building.
October 24, 2023 – Construction continues on the new superintendent’s office building. The crew has begun working to install footings for the new building.
October 24, 2023 – Construction continues on the new superintendent’s office building. The crew has begun working to install footings for the new building.
November 8, 2023 – Construction continues on the new superintendent’s office building. The crew has finished the foundation for the new building.
November 8, 2023 – Construction continues on the new superintendent’s office building. The crew has finished the foundation for the new building.
November 8, 2023 – Construction continues on the new superintendent’s office building. The crew has finished the foundation for the new building.
November 8, 2023 – Construction continues on the new superintendent’s office building. The crew has finished the foundation for the new building.
December 5, 2023 -- The crew works to lay concrete for the flooring of the new superintendent's office.
December 5, 2023 -- The crew works to lay concrete for the flooring of the new superintendent's office.
December 5, 2023 -- The crew works to lay concrete for the flooring of the new superintendent's office.
December 5, 2023 -- The crew works to lay concrete for the flooring of the new superintendent's office.
December 5, 2023 -- The crew works to lay concrete for the flooring of the new superintendent's office.
December 7, 2023 -- Concrete work continues as the driveway for the new superintendent's office takes shape.
December 7, 2023 -- Concrete work continues as the driveway for the new superintendent's office takes shape.
January 29, 2024 -- Construction continues as the steel skeleton is assembled for the new superintendent's office.
January 29, 2024 -- Construction continues as the steel skeleton is assembled for the new superintendent's office.
February 6, 2024 -- Construction continues as concrete flooring is poured for the storage mezzanine.
February 6, 2024 -- Construction continues as concrete flooring is poured for the storage mezzanine.
February 6, 2024 -- Construction continues as concrete flooring is poured for the storage mezzanine.
February 6, 2024 -- Construction continues as concrete flooring is poured for the storage mezzanine.
February 13, 2024 -- Construction continues as metal sheeting is going up, around the building.
February 13, 2024 -- Construction continues as metal sheeting is going up, around the building.
February 13, 2024 -- Construction continues as metal sheeting is going up, around the building.
March 6, 2024 -- Crews continue exterior work on the new superintendent's office.
March 6, 2024 -- Crews continue interior work on the new superintendent's office. First level, seen here.
March 6, 2024 -- Crews continue interior work on the new superintendent's office. Second level, seen here.
March 6, 2024 -- Crews continue interior work on the new superintendent's office. Second level, shop view, seen here.
March 6, 2024 -- Crews continue exterior work on the new superintendent's office.
March 19, 2024 -- The crew continues work as the new lettering is added an additional exterior work is completed.
March 20, 2024 -- Drywall is in the process of being hung. All exterior doors and windows are now installed.
March 20, 2024 -- Drywall is in the process of being hung. All exterior doors and windows are now installed.
March 20, 2024 -- Drywall is in the process of being hung. All exterior doors and windows are now installed.
March 20, 2024 -- Drywall is in the process of being hung. All exterior doors and windows are now installed.
May 29, 2024 -- Construction is complete and employees have moved into their new home.